INCREASED INVESTMENT BY OMAN OIL COMPANY IN BORL
INAUGURATION OF UC, IP TELEPHONY AND SHARE POINT PORTAL AT BORL
HYDROCRACKER REACTORS FOR BORL REACHED KANDLA PORT
MECHANICAL COMPLETION OF SINGLE POINT MOORING SYSTEM
BORL PROJECT PROGRESS CROSSES 85%
AGREEMENT FOR OPERATING BORL VIVEKANANDA KENDRA HOSPITAL
INAUGURATION OF BORL INTRANET SITE
SHRI. ASHOK SINHA (C&MD BPCL AND CHAIRMAN BORL) VISITS BINA REFINERY SITE
PHENOMENAL PROGRESS ACHIEVED FOR BORL
BORL CARES FOR ITS EMPLOYEES – MOU SIGNED FOR ESTABLISHING SCHOOL AT BINA TOWNSHIP
ANOTHER FEATHER IN THE CAP FOR BORL - 54 FLATS COMPLETED AND READY FOR POSSESSION
BORL CREATES HISTORIC MOMENT WITH SAP GO LIVE
HONORABLE MINISTER VISITS BINA REFINERY SITE
BORL Signs Agreement Of Mortgage Deed With State Bank Of India
BORL-SAP PROJECT IMPLEMENTATION TAKES OFF ON FAST TRACK!
CONTRACT FOR HYDROGEN GENERATION PLANT
CONTRACT FOR LAYING OF 935 KM VADINAR-BINA PIPELINE AWARDED
CONRACT FOR COKE CHAMBERS AND ASSOCIATED FACILITIES FOR BORL AWARDED
COMMERCE & INDUSTRY MINISTER OF MP VISITS BINA REFINERY SITE
Award of Contract for Line-pipes of Vadinar-Bina Crude oil Pipeline
Hydrocracker Reactor Order Placement to CPTDC
Captive Power Plant (CPP) Order Placement to BHEL

 